C250

Reduction In Maintenance

FAR #
88
Hydro-Mining
Magnetite
Field application reports

Objective

Deliver the same duty as the previous installed pump whilst providing a longer run time between failures.

Problem

Low run times and premature failures experienced by the client.

The Final Results

The CURVE™ C250 delivered the same duty as the previous installed pump whilst providing a longer run time between failures.

R476K Saved TCO

75% Reduction in Maintenance

56% Saved in Annual Spares