C250

Achieving Failure Free Operation

FAR #
68
SLG Cyclone Feed
Coal
Field application reports

Objective

To provide the client with a greater life span achieved out of the pump, while also minimizing the maintenance activities on the pump itself

Problem

The client had experienced premature failures and a large amount of maintenance activities with the prior pump

The Final Results

The CURVE™ C250 reduced maintenance required on the pump and lowered the Total Ownership Cost, with a wet-end inspection being the only maintenance activity that took place.

145% Longer Lifespan

R101K Saved in Annual Cost

41% Saving in operational costs

DOWNLOAD PDF

Looking For A New Solution?

Find a specialist near youview our products